Tag Archives: retainage

Know Your Rights – Limitations on Retainage for Private Construction Projects

By on November 20, 2017

The Massachusetts Retainage Act limits the amount of retainage allowed for private construction projects, and imposes mandatory processes for reaching the date of substantial completion, submitting punchlists and completing punchlist items, and submitting applications for payment and obtaining payment of retainage.

The Act applies to all construction contracts signed after November 4, 2014, for privately owned projects where the original contract price with the owner is at least three million dollars and the general contractor, subcontractors, or design professionals would have mechanic’s lien rights , but exempts residential housing projects of one to four units.

Limit on Retainage

Under the Act, no more than five percent retainage may be withheld from any progress payment. Among other things, this prohibits frontloading retainage amounts for a portion of the project, with less held at the end.

Substantial Completion

The Act defines substantial completion as the stage in the project when the work required under the general contractor’s contract with the owner is “is sufficiently complete … so that the project owner may occupy or utilize the work for its intended use.” Substantial completion may apply to the entire project or to a phase of the project, but only where the project owner has expressly allowed substantial completion for defined phases.

In order to reach substantial completion, the general contractor must submit a form for notice of substantial completion, as contained in the Act, to the owner within fourteen days of reaching the stage when the general contractor believes the project is substantially complete. Then the owner has fourteen days to accept or reject the general contractor’s notice. Should the owner fail to timely respond to the notice, the owner is deemed accept to general contractor’s work as substantially complete.  If the owner accepts the notice, the date of substantial completion is set and is binding upon all related aspects of the contract. If the owner rejects the notice, it must notify the general contractor in writing of the rejection and include the factual and contractual basis for the rejection and a certification that the rejection is made in good faith. The Act permits an expedited process for the general contractor to dispute the rejection under the contract’s dispute resolution procedures. Alternatively, the general contractor can resubmit a form for notice of substantial completion to the owner for new approval.

Submission of Punchlists and Completion of Punchlist Items

Within fourteen days after acceptance (whether express or deemed accepted) of the notice of substantial completion, or the final and binding resolution of a dispute, the owner must submit a written punchlist “describing all incomplete or defective work items and deliverables” to the general contractor. The owner’s punchlist must be certified as made in good faith.

The general contractor has an additional week after the owner’s deadline expires, or twenty-one total days after acceptance, to submit a punchlist to each subcontractor from whom the general contractor is holding retainage “describing all incomplete or defective work items and deliverables required,” which may include items in addition to the owner’s punchlist. The general contractor’s punchlist to its subcontractors and suppliers must be certified as made in good faith. General contractors, subcontractors and suppliers are permitted to dispute punchlist items directed to them.

Submitting Applications for Payment and Obtaining Payment of Retainage

The general contractor, subcontractors and suppliers from whom retainage is held may submit written applications for payment of retainage no sooner than 60 days following the date of substantial completion.  Each contractor shall use the form required by their contract to apply for payment of retainage. Alternatively, the project owner and general contractor may allow for earlier submission dates. An application for payment of retainage must include the punchlist, along with a written list identifying which items have been completed, repaired or delivered, and a certification that the application is submitted in good faith.

Applications for retainage must be paid within thirty days of receipt, minus any withholdings described below. For each tier of contract below the prime contact with the owner, the time period for paying retainage is extended by seven days.

Should the owner or contractor seek to withhold payment of retainage, they are limited to (1) the value of incomplete, incorrect or missing deliverables as either agreed upon by the parties or, if no agreement is reached, no more than two and a half percent of the total adjusted contract price; (2) one hundred and fifty percent of the reasonable cost to complete or correct incomplete or defective work items; and (3) the reasonable value of claims and any costs, expenses, or attorneys’ fees incurred as a result of the claims (but only when permitted by the terms of the contract).

Retainage, or any portion thereof, cannot be withheld unless the party seeking payment receives, before the date payment is due, a written explanation “of the incomplete or defective work items and incomplete, incorrect or missing deliverables, the factual and contractual basis for the claims and the value attributable to each incomplete or defective work item, deliverable and claim.” The explanation of withholding must also be certified as made in good faith.

Moreover, the Act prohibits the owner from holding any portion of retainage due to subcontractors or suppliers that are not the subject of the owner’s claim against the general contractor, unless the owner has declared the general contractor in default under its contract.

As the foregoing makes plain, the Act requires all parties to a project to adhere to strict guidelines in connection with withholding, and later releasing retainage.  In order to gain a full understanding of how the Act and other statutes govern Massachusetts construction projects, and how to preserve your rights under those statutes, contractors would be wise to consult with a Massachusetts construction attorney regarding their specific contract and situation.

Five for Fighting:  Subcontract Provisions Every Subcontractor Must Know to Get Paid

By on September 2, 2015

While there are any number of subcontract provisions that subcontractors must be aware of in order to negotiate subcontracts favorably, the following five provisions are critical to insuring that your business gets paid for the work it performs.

Lien Provisions

Did you know that it’s perfectly legal to relinquish your statutory right to a mechanic’s lien in New Hampshire?  If you did, give yourself a small pat on the back.  All too often, however, subcontractors – especially those new to working in New Hampshire – fail to appreciate that they can waive their right to assert or maintain a mechanic’s lien through their subcontract.  Worse still, it is often the case that subcontractors learn this valuable piece of information at the very worst time:  when they need to secure a mechanic’s lien for delinquent payment on a project.

In order to avoid this painful result, have your subcontracts reviewed carefully in-house or by your attorney, with a specific focus on any provision or language that relates to waiving or relinquishing the right to assert, maintain or perfect a lien or an attachment against the owner or its property.  If you see it, don’t accept it.  The mechanic’s lien is a very useful tool to make sure you get paid in New Hampshire, and you shouldn’t give it away before you start your project.   

Retainage Provisions 

Most every project contains a retainage provision, so how different could they be?  If you treat retainage provisions interchangeably, you may go a long time before you get paid that all important final five to fifteen percent of your contract balance.

Retainage provisions are like Skittles:  many flavors and some are better than others.  For example, if you’re a subcontractor that performs work early on in a project, it will be beneficial to negotiate retainage reductions based on acceptance of your scope of work by the project owner.  If you accept a common retainage provision that simply calls for the owner to withhold ten percent until the completion of the project, and you’re responsible for clearing the site and preparing for building or paving, it may be years before your final retainage payment becomes due, let alone gets paid.  Surely, that final ten percent looks better in your pocket than the owner’s.  As a result, it’s imperative that you closely monitor the retainage provision in each subcontract you execute.

Retainage isn’t intended to be an annuity that you receive years after you perform your work, but instead should provide the owner some security that you’ll finish your scope of work after you’ve been paid the majority of your contract balance.  If you focus on negotiating a retainage provision that fairly accounts for your scope of work and its timing in connection with the overall project, you shouldn’t need to wait extended periods of time to receive the final payment you’re owed. 

Change Order Provisions

There are virtually as many change order provisions as there are subcontracts.  It seems that every general contractor or construction manager that doesn’t utilize an AIA subcontract document creates its own change order provision.  With so many iterations of a provision meant to capture the same thing, more or less, what should your company be looking for? 

In short, to maximize your chances of getting paid for extra or change work, subcontractors should strive to negotiate change order provisions that come as close as possible to mirroring the reality of performing work on a project.  More often than not, that reality is a fast-paced project with a limited schedule where changed or extra work cannot wait weeks for signed change orders from executive level corporate representatives.  As a result, subcontractors are best served by negotiating change order provisions whose terms are not unduly burdensome, restrictive or otherwise difficult to satisfy. 

For instance, the author recently reviewed several subcontracts which directed that only the company president or another board level executive were authorized to approve a change in scope.  This is hardly practical for a subcontractor.  Ordinarily, a general contractor’s executives are not in the field regularly, and do not have the kind of “hands on” knowledge of a project that a project manager or superintendent possesses.  Worse still, executives are not readily available to subcontractors, as a general matter.  As a result, it’s not difficult to anticipate the difficulties that a subcontractor is likely to face when trying to balance the need to perform change order work, to maintain the project schedule and to secure the appropriate written authorization to perform the work.  These competing interests often lead to subcontractors performing work before they are authorized to do so according to the terms of their subcontracts, based on spoken assurances from onsite representatives of the general contractor.  This, in turn, exposes the subcontractor to the risk that the general contractor or the owner will reject the change order and that a fight will be necessary to get paid.

Because the competing interests in performing the work, meeting the schedule and securing appropriate authorization for changes in scope exist on so many projects, subcontractors are best served by negotiating change order provisions that mirror, as closely as possible, the anticipated conditions in field.  Doing so will go a long way toward insuring that you’ll be paid for your extras.  To the extent that you have any doubt regarding what steps are necessary to make sure you’re complying with the change order provision in your subcontract, you’re well advised to speak with your construction attorney.

Pay if Paid Provisions

Construction lawyers frequently discuss the concept of “risk allocation” with their clients.  So what is risk allocation?  At is core, risk allocation is concept used to describe how the parties to a contract divide or allot the various risks attendant to a particular contract. 

 A “pay if paid” provision is a tool used by general contractors and constructions managers to reallocate the risk of nonpayment, that for many years, was borne by the general contractor or construction manager.  A “pay if paid” provision operates exactly as it sounds.  That is, it’s a provision that conditions payment to a subcontractor for work it performs on the upstream contractor first receiving payment from the owner, or from the party upstream from it.  In other words, if the general contractor doesn’t get paid from the owner, the general contractor has no obligation to make payment to its subcontractor, regardless of whether the subcontractor fully and dutifully performed its work.

Does it make sense for a subcontractor to accept a “pay if paid” provision in its subcontract?  The answer is unequivocally no.  The vast majority of subcontractors have no ability to determine the financial solvency of the owner or the dependability of its construction financing.  Furthermore, a subcontractor has no direct contract with the owner, as the general contractor does, which thereby limits the subcontractor’s potential legal remedies if the owner elects not to pay for any number of reasons that have nothing to do with the subcontractor.  Because of these issues and others, subcontractors should be reticent to execute any contract that contains “pay if paid” language.  Because “pay if paid” language can be difficult to discern from other kinds of risk allocation devices, such as “pay when paid” and similar provisions, if you have any doubt about what your contract specifies seek the advice of your construction attorney.

Attorney’s Fees Provisions

Last, but certainly not least, subcontractors must understand what the attorney’s fees provisions mean in their subcontracts.  Like all of the foregoing types of provisions, there isn’t a one size fits all remedy.  What stands out about the importance of an attorney’s fee provision is that in some very important instances, the only way to enforce or determine your rights with respect to each of the kinds of provisions discussed above, is to employ the services of an attorney.  And that costs money.  So, if you don’t have an adequate provision of this kind, you’ll be forced to decide whether or not to pursue claims for payment (or other claims) based not upon whether you’re entitled to be paid, but rather by how much you’ll have to spend to get paid.

This isn’t lost on some less scrupulous general contractors.  In some instances, if a general contractor knows you’ll have to spend enough money to chase payments you’re owed that it becomes throwing good money after bad, they’ll simply pocket the money you should be paid and force you to bring suit against them.  This is no way to keep your projects profitable.

In order to make sure that you don’t fall victim to this scenario, insure that your contract has an attorney’s fees provision that calls for your fees to be paid in the event that you need the services of an attorney to enforce your rights under your subcontract.

So what do you do when the general contractor won’t agree to an attorney’s fee provision that runs in your favor?  In that instance, you negotiate what is known as a “prevailing party” provision.  A “prevailing party” provision calls for either party to a contract to receive their attorney’s fees and other costs from the other side in the event that a particular party prevails in an arbitration or lawsuit.  As is the case with each of the foregoing kinds of provisions, the devil is in the details of the provision.  Nevertheless, if you’re diligent about reviewing (or having someone else review) the language of any proposed attorney’s fee provision, you’ll be much less likely to learn that your subcontract only gives the general contractor the right to recover its attorney’s fees. 

If you master the foregoing five kinds of provisions, or engage your construction attorney to help you do so, you will negotiate better subcontracts before you get started and you’ll almost certainly forestall a variety of construction disputes before they have the opportunity to ripen.  Should you have questions regarding any of the information presented here, you’d be well advised to contact your New Hampshire or Massachusetts construction attorney.

Proposed Changes to The Retainage Law for Massachusetts Private Construction Projects

By on June 30, 2015

*with contributions from Christopher D. Strang

In November 2014, the Massachusetts Legislature passed Mass. Gen. Law c. 149, § 29F, entitled “Payment of Retainage in Private Construction Projects” (“The Retainage Law”).  The Retainage Law reduced the amount of retainage that can be withheld on many large private construction projects. It also provides deadlines for paying retainage amounts and methods for determining the date of substantial completion.  The Massachusetts Senate recently held hearings on proposed Bill Number 1006, which seeks to amend the statutory language of this law.

Under the changes proposed in Bill 1006, The Retainage Law would be limited in its application and would only control the amount of retainage withheld on certain private construction projects. Below is an explanation of the standards The Retainage Law currently sets forth, followed by an explanation of the changes Bill 1006 proposes.

Projects Covered by The Retainage Law

The Retainage Law applies to all private construction contracts entered into after November 6, 2014 valued over $3 million dollars, with the exception of residential projects for four or fewer units.

Limitations on Retainage

Retainage is specifically limited to 5% of each periodic payment. Contracts that either waive, limit or subvert the 5% retainage cap may be void and unenforceable under the statute.

Notices of Substantial Completion

Under The Retainage Law, general contractors must submit a “Notice of Substantial Completion” to the owner within 14 days of determining that it has achieved substantial completion. The statute defines “substantial completion” as the stage in the project where the project work is sufficiently complete as to permit the owner to occupy or utilize the premises for its intended use. Substantial completion may be applied to the project as a whole or to a phase of the entire project where the contract permits substantial completion for project phases.

The owner then has 14 days to notify the general contractor whether it accepts or rejects the Notice of Substantial Completion. To reject it, an owner must notify the contractor in writing and include “the factual and contractual basis for rejection,” along with a certification that the rejection was made in good faith. Rejection of the Notice of Substantial Completion permits the contractor to utilize the dispute resolution procedures provided for in the contract, which must begin within 7 days after the rejection (unless the contractor later resubmits a Notice of Substantial Completion). If the owner fails to deliver notice of its rejection within 14 days, or fails to comply with the requirements of Section 29F(d), the date indicated by the contractor in the Notice of Substantial Completion will be deemed accepted by the owner.

The owner has 14 days from the date the Notice of Substantial Completion is accepted to submit a written punchlist to the contractor. The punchlist must describe all incomplete or defective work items and deliverables required of the contractor, and include a certification that it is made in good faith. A “Deliverable” is defined by Section 29F(a) as “a project close-out document that shall be submitted by the [contractor] seeking payment of retainage under the [contractor’s contract] for construction; provided, however, that a lien waiver or release, which is a deliverable, shall comply with chapter 254; and provided further, that ‘deliverable’ shall not include any document affirming, certifying or confirming completion or correction of labor, materials or other items furnished or incomplete or defective work.” The contractor must then pass on a written punchlist to each subcontractor it is holding retainage against within an additional 7 days (or 21 days after the date the Notice of Substantial Completion is accepted), detailing all incomplete or defective work items and deliverables. The punchlist to the contractor’s subcontractors may include items beyond those on the owner’s punchlist and must also include a certification that it is made in good faith. Both the general contractor and subcontractors are permitted under The Retainage Law to dispute the items listed on punchlists.

Applications for Payment of Retainage

General contractors and subcontractors must submit a written application for payment of retainage within 60 days after the date of substantial completion for a final and binding resolution regarding a disputed date. This application must include a written list of all punchlist items that were completed, repaired, and delivered, and must be certified by the submitting party that it was made in good faith.

The owner then has 30 days to provide payment of retainage to the contractor. When providing payment of retainage, owners are permitted to withhold portions of the retainage to cover incomplete or defective work, limited by the following:

  • for incomplete, incorrect or missing deliverables, either (a) the value of the deliverable, as mutually agreed upon in writing between the owner and contractor or (b) if no value has been agreed upon, the reasonable value of the deliverables, not to exceed 2.5% of the total adjusted contract price;
  • 150% of the reasonable cost to complete or correct incomplete or defective work items; and
  • the reasonable value of claims and any costs, expenses and attorney’s fees incurred if the claim is allowed under the contract.

Portions of retainage may only be withheld where the contractor seeking payment received a detailed punchlist from the owner prior to the date payment is due. The time period for payment under an application for payment is extended by a period of 7 days for the contractor at each tier of contract below the general subcontractor. Contractors may submit further applications for payment of retainage as work is completed on the project. The Retainage Law specifically prevents owners from withholding retainage payments otherwise due to subcontractors where the general contractor is not in default. General contractors have 7 days to forward retainage payments to subcontractors.

At a minimum, The Retainage Law requires applications for payment of retainage to be submitted at least once a month. Rejection of an application is also subject to dispute resolution procedures, which may be initiated 30 days after the rejection of an application for payment of retainage.

Bill No. 1006 – Proposed Changes to The Retainage Law

Bill 1006, if passed, will dramatically change the scope and effect of The Retainage Law. It would add exemptions for construction projects which are financed or supported, in whole or in part, by state or federal mortgage assistance, special taxing arrangements, tax credits, grants, issuance of bonds, loans, loan guarantees, debt, or equity assistance.

It also proposes removing the sections relating to notices of substantial completion and applications for payment of retainage entirely. Bill 1006 would reduce The Retainage Law to the following content: (1) retainage is limited to 5% of the contract price and (2) contracts which require or permit retainage in excess of 5% of the contract price will be void and unenforceable insofar as any such excess is concerned.

Impact of The Retainage Law and Bill No. 1006

Citing practical issues with meeting the deadlines set forth in The Retainage Law, some project developers and owners have articulated a desire to remove large portions of it. In particular, they cite the 14-day limitation to accept or reject the date of substantial completion as impractical and unachievable. Some general contractors criticize the additional 7 days for paying subcontractors, and for completing and forwarding punchlists. Some also claim the law does not adequately consider the complexity of communication between multiple parties on large projects.

Bill 1006 alters the language that retainage may not exceed 5% of “any progress payment” to state that retainage may not exceed 5% “of the contract price.” While the amount would equal out at the end of the project, the proposed changes would arguably allow an owner or higher tiered contractor to withhold more than 5% from any single payment, so long as the amount equals 5% of the total contract price. Such a change could negate the benefit contractors receive through larger progress payments throughout a project, but would have no impact on the amount of retainage outstanding at the end of the project.

Whether Bill 1006 will be enacted and what additional changes, if any, are to be made to the Retainage Law will be determined over the next several months. It is clear that there is significant interest in creating consistency in retainage guidelines for the construction industry.

The foregoing information is a general summary regarding proposed changes to retainage in private construction projects in Massachusetts. If you are uncertain about anything regarding the amount of retainage withheld on a project or the process of obtaining payment for retainage amounts, contact your construction attorney to ensure the necessary steps are taken to achieve the best possible outcome.

 

What Every Massachusetts Subcontractor Must Know to Limit Risk and Get Paid for Work in New Hampshire

By on February 2, 2015

Massachusetts subcontractors securing work in New Hampshire will encounter an unfamiliar legal landscape containing more than one trap for the unwary. In order to strike a fair deal and to put your business in the best position to get paid for your work, every subcontractor should be aware of certain basic differences in laws of the Granite State.

Put Your Business in “Good Standing”

Before any foreign based entity can transact business in New Hampshire, it must be registered with the Secretary of State. The process for registering your business is relatively straightforward and requires that the entity file several basic documents, pay a filing fee and name a registered agent in New Hampshire to accept service of process on behalf of the foreign entity. After complying with the Secretary of State’s requirements, your business will be in Good Standing with the State of New Hampshire and ready to move forward with projects in New Hampshire.

Striking a Fair Deal

In order to reach an agreement with a general contractor or construction manager that your business can live with and live up to, you need to know the laws that govern your contract. New Hampshire law varies in important ways from its counterpart in Massachusetts. Being familiar with some of the basic and important distinctions in the law will put your business in a better position to compete and succeed on your subcontracts.

One of the more important distinctions of which to be mindful is that in New Hampshire a subcontractor can waive its right to assert a mechanic’s lien against a project by contract. Because many general contractors, construction managers and savvy owners in New Hampshire know this, these waiver provisions are found commonly in contracts provided to subcontractors. Because Massachusetts law prohibits these provisions, subcontractors agreeing to perform work in New Hampshire must devote full attention to this detail, in order to avoid extinguishing mechanic’s lien rights unknowingly. If any doubts linger about whether a particular provision in a contract will result in a waiver of lien rights, it is important to consult your attorney.

Another important distinction exists with respect to conditional payment provisions, often known as “pay-if-paid” or “pay-when-paid.” With the enactment of the Massachusetts Prompt Payment Act in 2010, subcontractors gained significant rights in private contracting that were formerly the subject of bargaining between the parties. One of the chief among those rights is that in private construction projects with a prime contract in excess of three million dollars, so-called pay-if-paid provisions are unenforceable except in two rare instances. Since the enactment of this statute, pay-if-paid provisions in Massachusetts rarely result in significant losses to subcontractors.

In New Hampshire, however, no prompt payment act or functional equivalent has been enacted, and the New Hampshire Supreme Court has not addressed the pay-if-paid issue directly. Accordingly, significant uncertainty remains regarding the enforceability of these provisions in all private construction contracts, and subcontractors are wise to avoid or limit these provisions when possible.

Working in tandem with the Prompt Payment Act, the recently enacted Massachusetts Retainage Act limits owners and general contractors withholding retainage to no more than five percent on each progress payment on private construction contracts of three million dollars or more. Like the Prompt Payment Act, New Hampshire has no equivalent law to the Retainage Act. As a result, retainage provisions in construction contracts are subject to bargaining, and general contractors and owners commonly propose withholding retainage of ten percent or more. Because these provisions are not subject to any maximum by law, subcontractors should endeavor to negotiate these provisions down or, at a minimum, negotiate a phased release of retainage over the course of a project. Reducing or phasing retainage is vitally important for subcontractors that perform work at the inception of a project, like site work contractors, because commercial contracts commonly direct that withheld retainage be released only after completion of the entire project, and not after completion of a particular subcontractor’s work. As a practical matter, this can mean months or years of delay until retainage is released if the retainage provision is not drafted or revised to avoid this result.

Getting Paid

Subcontractors that avoid waiving lien rights, avoid pay-if-paid provisions, and negotiate fair retainage schedules have taken important steps toward getting paid for completed work. The job isn’t done completely, however, as important steps remain to secure payment. Most notably, subcontractors are well advised to take steps to preserve their mechanic’s lien rights at the outset of a project and during its duration as New Hampshire’s mechanic’s lien law and procedure are markedly different from that encountered in Massachusetts.

New Hampshire mechanic’s lien law draws an important distinction between those that have a direct contract with the project owner (usually the general contractor) and those that do not (subcontractors and suppliers). If you fall into the latter category, as a first or second tier subcontractor or supplier, you must have a contract with the general contractor or first tier subcontractor and provide the project owner written notice of your lien rights. Ostensibly, the law requires the written notice to prevent the owner from becoming subject to liability for claims asserted by parties that were unknown to the owner. As practical matter, providing written notice to the owner of lien rights is a matter of preserving a subcontractor’s ability to establish, perfect and maintain a mechanic’s lien on a project in the event that payments are late or aren’t coming at all.

In New Hampshire, a subcontractor’s right to assert and enforce a mechanic’s lien is directly tied to when the subcontractor provides the required notice of lien rights. In an ideal world, subcontractors would provide the required notice to the owner at the outset of the project, preserving the full value of their lien. More frequently than not, however, subcontractors fail to send the owner notice of lien rights until after beginning work and a problem has arisen. When that occurs, a subcontractor’s lien rights are limited to the amount remaining due from the owner or general contractor to the party upstream of the subcontractor. In other words, the subcontractor’s lien is good only to the extent of any payment remaining due to the party from which the subcontractor will be paid when notice is given to the owner. This can be problematic when payments slow down or stop completely toward the end of a project and the subcontractor failed to provide notice of its lien rights at the beginning of the project, because notice may arrive at a time when little or nothing remains due to the party from which the subcontractor seeks payment through its contract. In that instance, even if the subcontractor has complied in all other respects with its contractual obligations, no valid lien exists in connection with its work on the project. As a result, the importance of providing early notice of lien rights to the owner cannot be overstated.

The lien process has other pitfalls for uninitiated. In New Hampshire, mechanic’s lien rights are valid and enforceable for only 120 days following the subcontractor’s last date of work, or delivery of materials in the case of a supplier. Ordinarily, a subcontractor’s last date of work is calculated from the point of substantial completion of the subcontractor’s work, and closing punch list items or returning to the project to remedy deficient or defective work will not support an extension of the 120 day deadline to perfect the lien.

In order to perfect a mechanic’s lien, subcontractors must file suit in court, petition the court for a mechanic’s lien attachment and record the lien with the Registry of Deeds in the county in which the project is located within the 120 day period subsequent to substantial completion. Failure to do any of the foregoing is fatal to enforcing a mechanic’s lien.

So, given the complexities associated with establishing and perfecting a lien in a timely fashion, why do it when the general contractor or owner will simply “bond it off?” The simple answer is that in New Hampshire the prevailing law does not compel a subcontractor to accept alternate security for its perfected lien. As a result, owners and general contractors cannot force a valid mechanic’s lien to be discharged solely on the basis of providing alternate security for subcontractors’ claims. In many circumstances, there are very good reasons why subcontractors prefer to maintain mechanic’s liens rather than accepting bonds or other security. For a more detailed recitation of those reasons, or to understand mechanic’s lien law in New Hampshire in greater detail, please consult a New Hampshire construction attorney.  

Corey-cropped - 2