Articles/Publications

Show Me the Money: Getting Paid on Federal Public Construction Projects

By on July 18, 2016

It is imperative that subcontractors and material suppliers seeking payment for completed work on federal-level public construction projects be aware of the paradigm of laws and policies that exist governing such matters. To start, The Miller Act, codified as 40 U.S.C. §§ 3131-3134, exists to provide subcontractors on federal-level public construction projects a means by which to secure their right to payment in an analogous manner to how M.G.L. c. 149, § 29 operates to provide Massachusetts subcontractors and material suppliers on state-level public construction projects a means by which to secure the same. Specifically, the Miller Act requires general contractors on federal projects to provide performance bonds and payment bonds to the awarding authority where the prime contract exceeds $100,000. (for a comprehensive overview of subcontractor Miller Act rights see, “Federal Subcontractors – Understanding the Basics of Your Rights Under the Miller Act.”). 

While the legal framework behind federal-level public construction projects and state-level public construction projects often operate in tandem it is imperative to note that Federal law and Massachusetts law treat the enforceability of “pay-if-paid” and “pay-when-paid” subcontract clauses somewhat differently. This distinction is one that subcontractors need be wary of when entering into public construction contracts.

“Pay-if-paid” clauses create a condition precedent to subcontractor payment. That is, a subcontractor has no right to payment for completed work until the general contractor has received payment from the owner. “Pay-when-paid” clauses create no such condition precedent to subcontractor payment. Rather, the general contractor has a ‘reasonable time’ to obtain payment from the project owner, but in the event the owner does not pay the general contractor within the ‘reasonable time’ the subcontractor still has the right to seek payment from the general contractor. Ambiguous contract language often complicates the subtle, yet substantial, differences between the two types of clauses leading to high stakes contract interpretation disputes.

In 2004, Massachusetts did away with the fraught distinction between “pay-if-paid” and “pay-when-paid” clauses on state-level public construction projects. See, Framingham Heavy Equip. Co., Inc. v. John T. Callahan & Sons, Inc., 807 N.E.2d 851, 855 (Mass. App. 2004). Thus with regard to Massachusetts state-level public construction projects “pay-if-paid” causes have been effectively eliminated in favor of “paid-when-paid” clauses.” 

Federal-level public construction projects, on the other hand, have not completely eliminated the distinction between “pay-if-paid” and “pay-when-paid” contract clauses. Thus, on federal-level public construction projects “pay-if-paid” language included in a subcontract could complicate subcontractor recovery in relation to the principal contractor. The limited amount of Federal case law on the issue, however, leads to the inference that Federal Courts disfavor allowing “pay-if-paid” clauses to operate in the federal-level public construction context, particularly on Miller Act projects.

According to Federal Courts in both the First and Ninth Circuits, “the Miller Act is ‘highly remedial in nature,’ and should be construed and applied liberally to ‘effectuate the Congressional intent to protect those whose labor and materials go into public projects.’” United States ex rel. J.H. Lynch & Sons v. Travellers Cas. & Surety Co. of Am., 783 F. Supp. 2d 294, 296 (D.R.I. 2011) quoting, United States ex rel Walton Tech., Inc. v. Weststar Eng’g, Inc., 290 F.3d 1199, 1209 (9th Cir. 2002). Furthermore, according to the reasoning of the Ninth Circuit, because the Miller Act itself conditions payment, not on whether prime contractor is paid, but rather, whether the subcontractor has performed AND whether the statutory amount of time to bring a Miller Act claim has passed, it then follows that the terms of the Miller Act trump subcontract “pay-if-paid” language absent a “clear and explicit” waiver on the part of the subcontractor. Of particular note, the Ninth Circuit, specifically states, and the District Court of Rhode Island, located in the First Circuit, specifically quotes, the following language; “A subcontractor that has performed as agreed need not await the Government’s payment of the contractor before initiating an action under the Miller Act against the contractor or the surety.” United States ex rel Walton Tech., Inc. v. Weststar Eng’g, Inc., (9th Cir. 2002); United States ex rel. J.H. Lynch & Sons v. Travellers Cas. & Surety Co. of Am., (D.R.I. 2011).

The law is far from settled regarding the enforceability and distinction between “pay-if-paid” and “pay-when-paid” subcontract clauses on federal-level public construction projects. While there is some guidance on this issue in the context of the Miller Act, the distinction between the two clauses may still prove thorny for subcontractors seeking to enforce their right to payment.  Thus, subcontractors should keep an eye towards the development of the law in this area as it is likely that more distinct legal trends will begin to emerge. If you have any questions about payment issues on public construction projects you should contact a Massachusetts construction lawyer.

Andrea Jacobs
Ms. Jacobs is an associate of the firm whose practice focuses on civil litigation and transactional law in a variety of business areas. She represents clients in all stages of civil litigation, including mediations and arbitrations, and has specific experience with public and private construction litigation, business defamation, and general business disputes.
Andrea Jacobs on EmailAndrea Jacobs on Linkedin